Officials are working toward repurposing Faubion Elementary for New Hope High School. (Rendering courtesy Leander ISD)
Leander ISD is moving forward with plans to repurpose the former Faubion Elementary campus into a new home for New Hope High School.
The board of trustees unanimously approved a $2.94 million contract with American Constructors for the first phase of the campus renovations at its Nov. 19 meeting.
Some context
The board last discussed the project in October when officials proposed a phased approach to repurposing the campus. The board had already advanced plans for Pfluger Architects to provide design services for the project in January.
Per agenda documents, Phase 1 would include completing 30,525 square feet focused on academic spaces, including a courtyard commons, maker space, media center, science lab, gym and fitness center, art lab and a learning commons.
Phase 1 design plans include two "neighborhoods" within the campus, breaking up academic spaces to a more personal scale.Courtesy Leander ISD
The update
Chief Operations Officer Jeremy Trimble said the contract approval will allow contractors to prepare the shell of the building and conduct demolition activities for the "core area" of the existing Faubion campus.
Looking ahead
The project's next steps will include a renovation permitting phase ahead of construction, which could take place between January and July. The goal is to open the campus for NHHS for the 2027-28 school year, Trimble said.
Phase 2 of construction could include 28,100 square feet focused on support spaces, with Phase 3 rounding out the project with the construction of a 59,740 square foot two-story building expansion.
Phases 2 and 3 could also include shared space for the Early College High School, which is still being considered to co-locate at the repurposed campus.