Construction on Hwy. 6 in Bryan-College Station continues as the Texas Department of Transportation works on a new traffic pattern for the week of Aug. 17. The new pattern is reported to begin Aug. 23.
What you need to know
- Aug. 18: Full closure of northbound lanes between Southwest Parkway and Briarcrest Drive, 7:30 p.m.-6:30 a.m.
- Traffic will be directed to exit Hwy. 6 at Southwest Parkway. Drivers may reenter south of Briarcrest Drive.
- These northbound entry ramps will also be closed: south of Southwest Parkway, Harvey Road and University Drive.
- Aug. 19: Full & single lane closures along Southwest Parkway, 7:30 p.m.-6:30 a.m.
- Full closure of northbound lanes between Briarcrest Drive and Southwest Parkway, 7:30 p.m.-6:30 a.m.
- Traffic will be directed to exit Hwy. 6 at University Drive. Drivers may reenter north of Southwest Parkway.
- These southbound entry ramps will also be closed: north of Briarcrest Drive, University Drive and Harvey Road.
- Single-lane closure of northbound lanes between Southwest Parkway and University Drive, 7:30 p.m.-6:30 a.m.
- TxDot will also close off the northbound mainland for material haul off.
- Full closure of northbound lanes between Briarcrest Drive and Southwest Parkway, 7:30 p.m.-6:30 a.m.
- Aug. 20: Full & single lane closures along Southwest Parkway, 7:30 p.m.-6:30 a.m.
- Full closure of southbound mainlanes between Briarcrest Drive and Southwest Parkway, 7:30 p.m.-6:30 a.m.
- Traffic will be directed to exit Hwy. 6 at University Drive. Drivers may reenter north of Southwest Parkway.
- These southbound entry ramps will also be closed: north of Briarcrest Drive, University Drive and Harvey Road.
- Single-lane and full closure of northbound lanes between Southwest Parkway and University Drive, 7:30 p.m.-6:30 a.m.
- TxDot will also close off the left northbound mainland for material haul off with a full closure between University and Briarcrest drives to set traffic barriers.
- Traffic will be directed to exit at University Drive’s northbound exit and may reenter south of Briarcrest Drive.
- The northbound entry ramp south of University Drive will also be closed.
- Full closure of southbound mainlanes between Briarcrest Drive and Southwest Parkway, 7:30 p.m.-6:30 a.m.
- Aug. 21: Full & single-lane closures along Southwest Parkway, 7:30 p.m.-6:30 a.m.
- Full closure of southbound mainlane between Briarcrest Drive and Southwest Parkway, 7:30 p.m.-6:30 a.m.
- Traffic will be directed to exit at the southbound University Drive off-ramp. Drivers may reenter north of Southwest Parkway.
- These southbound entry ramps will also be closed: north of Briarcrest and University drives and Harvey Road.
- Single-lane closure of northbound mainlane between Southwest Parkway and University Drive, 7:30 p.m.-6:30 a.m.
- TxDOT will close off this lane for material haul off.
- Full closure of southbound mainlane between Briarcrest Drive and Southwest Parkway, 7:30 p.m.-6:30 a.m.
- Aug. 23: Single-lane & full closure of northbound mainlane between Southwest Parkway and University Drive, 7:30 p.m.-6:30 a.m.
- Traffic will be directed to exit at the northbound University Drive off-ramp. Drivers may reenter south of Briarcrest Drive.
- The northbound entry ramp south of University Drive will also be closed.
- TxDOT will close this lane for material haul off and the full closure is scheduled for crews to designate a new traffic pattern.
Going forward
TxDOT began its $670 million “Big 6” project in December 2025 and is expected to continue through 2030.