Bryan-College Station will have multiple closures on Harvey Road and Harvey Mitchell Parkway due to the 'Big 6' construction, Nov. 9-12.
'Big 6' is a long-term Texas Department of Transportation project along Hwy. 6 through Bryan and College Station, aimed at helping the developing cities deal with growing traffic.
What you need to know
Nov. 9-11: Single-lane closure of the northbound frontage road from Harvey Road to University Drive, 7:30 p.m.-6:30 a.m.
The right lane will be closed for street cleaning operations.
The University Drive exit ramp and entrance ramp south of University Drive will be closed and drivers can re-enter the main lanes south of Briarcrest Drive.
Full closure of the northbound mainlanes from Harvey Mitchell Parkway to Harvey Road. All traffic must exit at Harvey Mitchell Parkway and re-enter using the entrance ramp south of Harvey Road.
Single-lane closure of the southbound left mainlane from Harvey Road to Harvey Mitchell Parkway for paving operations.
Two single-lane daytime closures off Harvey Road and University Drive Eastbound University Drive between the SH 6 frontage road and Veterans Parkway, 6 a.m.-3 p.m.
Nov. 12: Single-lane closure of the northbound frontage road from Harvey Road to University Drive, 7:30 p.m.-6:30 a.m.