Residents could soon see movement at Bastrop's Wastewater Plant No. 3, following a July 14 approval from Bastrop City Council to issue $11 million in certificates of obligation for the planning and design phases.
Why it matters
The decision launches the first phase of a $60 million infrastructure project that officials said is necessary to keep up with the area's rapid growth.
Zooming in
In a staff report, city Finance Director Judy Sandroussi said the debt issuance will not only finance the much-needed expansion, but will also create a new revenue stream for the city.
What's changing
Beyond basic wastewater treatment, the plant will produce potable water and reusable effluent that City Manager Sylvia Carrillo-Trevino said can be sold to industrial customers—a first for Bastrop.
Something to note