Central Austin drivers can expect closures and detours from I-35, Congress Avenue and other projects this month. (Jessica McLaren/Community Impact)
Central Austin’s transportation projects range from tunneling under I-35 and block-by-block work on Congress Avenue to early planning to extend light rail to the airport.
Ongoing projects
I-35 Capital Express Central: drainage tunnel and pump station
Project: 6.5 miles of 22-foot-wide drainage tunnels under I-35 from Airport Boulevard to Holly Street and along Cesar Chavez Street from I-35 to US 183, with a pump station at the end.
Update: Drop shaft work continues, and TxDOT expects both tunnel boring machines to be running by year’s end, starting near Airport Boulevard. The southbound I-35 frontage road at River Street stays closed through mid-2028, and the Levander Loop trail remains closed through 2028.
Timeline: mid-2025-2029
Cost: $746 million (tunnel contract)
Funding sources: Texas Department of Transportation, Capital Area Metropolitan Planning Organization
Cranes stand over TxDOT’s I-35 drainage tunnel work near Airport Boulevard, where both tunnel boring machines are expected to be running by year’s end.(Jessica McLaren/Community Impact)
Congress Avenue Urban Design Initiative: Phase 1
Project: Widens sidewalks, upgrades bike lane barriers, and adds trees, pedestrian zones and turn lanes from Cesar Chavez to Seventh streets.
Update: Work moves north about one block every three months. The 200 block is substantially complete, and 300-block work was expected to start in late October, according to the Downtown Austin Alliance. Drivers should expect short-term lane closures, but sidewalks and businesses remain open.
Timeline: January 2026-summer 2027
Cost: $13 million (Phase 1); $29 million (full project)
Crews stripe a crosswalk at Congress Avenue and Second Street as Phase 1 of the Congress Avenue Urban Design Initiative moves north.(Jessica McLaren/Community Impact)
Upcoming projects
Austin Light Rail: airport extension
Project: A roughly 3-mile, mostly elevated extension of light rail’s first phase, which runs down Guadalupe Street from E. 38th Street, running from the planned Yellow Jacket station on East Riverside Drive to Austin-Bergstrom International Airport.
Update: The Austin Transit Partnership announced Nov. 10 that it had begun planning the extension, which ATP dropped from its scaled-down 2023 plan. Planning will take up to a year. Light rail’s first phase is set to break ground in 2027.
Timeline: construction TBD
Cost: TBD
Funding source: TBD; federal funds are among options
The Austin Transit Partnership is planning a light rail extension to the airport.(Rendering courtesy of ATP)
Dean Keeton Street transit lane at I-35
Project: A center-running transit lane on Dean Keeton Street through the rebuilt I-35 frontage road intersection, part of TxDOT’s I-35 CapEx Central project.
Update: City Council committed $1 million Nov. 5. A city-state agreement on design and construction will follow. The lane is meant for buses such as CapMetro Rapid Route 837.
Austin has committed $1 million to a transit lane on Dean Keeton Street as part of the I-35 rebuild.(Ben Thompson/Community Impact)
I-35 Capital Express Central: Downtown segment
Project: Adds high-occupancy vehicle lanes, lowers the main lanes and rebuilds cross streets from MLK Jr. Boulevard to Holly Street, plus three pedestrian-only bridges.
Update: TxDOT says construction begins in early 2027, with the city’s cap and stitch elements, foundations for future park decks over the highway, phased in over time.
Timeline: 2027-33
Cost: part of the $4.5 billion I-35 CapEx Central budget