Bastrop County crews are back to work after a bee infestation delayed repairs to the courthouse roof.
The update
An Oct. 13 Commissioners Court report shows the completion deadline for roof work was extended from Sept. 5 to Dec. 4 because of a bee infestation, scheduling conflicts and weather.
What else?
As previously reported, officials are restoring the 1883 courthouse to its original appearance through a $23.4 million preservation project.
County officials said the historic restoration process began in 2022 and could take six to 10 years, placing potential completion between 2028 and 2032.