Dripping Springs ISD Administration relocation: 300 Sportsplex Drive, Dripping Springs
Type of work: renovation/alteration
Estimated cost: $7.5 million
Timeline: June 1, 2022-June 1, 2023
Scope of work: renovate existing elementary school into administration offices, child care facility and community spaces
ClearWater Express: East William D. Cannon Way, Austin
Type of work: new construction
Estimated cost: $3 million
Timeline: June 1, 2022-Feb. 28, 2023
Scope of work: new car wash facility
Wenty’s Wine Bar: 5307 Bell Springs Road, Ste. 200, Dripping Springs
Type of work: new construction
Estimated cost: $400,000
Timeline: June 1-Dec. 1
Scope of work: new construction of a 2,777-square-foot commercial building with a 1,523-square-foot patio on an existing vacant and undeveloped site
Lulu’s: 10402 Menchaca Road, Bldg. C, Austin
Type of work: renovation/alteration
Estimated cost: $134,000
Timeline: April 11-July 11
Scope of work: tenant improvement of existing white box space
Over Yonder Nature School: 5000 Bell Springs Road, Dripping Springs
Type of work: renovation/alteration
Estimated cost: $280,000
Timeline: April 4-Aug. 1
Scope of work: renovate existing residence to new preschool
Austin ENT South Clinic: 6503 Menchaca Road, Austin
Type of work: new construction
Estimated cost: $2.75 million
Timeline: Jan. 4, 2022-Jan. 30, 2023
Scope of work: Two-story medical office building with second-floor office over open parking garage using structural steel-framing supported by reinforced concrete foundation
Greenbelt Belterra: 165 Hargraves Drive, Ste. S120, Dripping Springs
Type of work: new construction
Estimated cost: $80,000
Timeline: May 1, 2022-Jan. 31, 2023
Scope of work: new construction of retail store
The Augustine: 707 W. Slaughter Lane, Austin
Type of work: new construction
Estimated cost: $50 million
Timeline: Sept. 12, 2022-April 9, 2024
Scope of work: apartments and parking garage
Rob Shelton Boulevard sidewalks: Shelton Lane and Sports Park Drive to Founders Park Road, Dripping Springs
Type of work: renovation/alteration
Estimated cost: $957,951
Timeline: Oct. 1, 2022-April 18, 2023
Scope of work: construct sidewalks, a crushed granite trail and one pedestrian bridge; striping bike lanes within existing pavement width
Townbridge Capital office building: 4800 W. Hwy 290, Sunset Valley
Type of work: new construction
Estimated cost: $4 million
Timeline: June 1, 2022-April 30, 2023
Scope of work: construction of a new two-story above-parking office building; building will be constructed as a conditioned shell with the build-out of an actual office area to be completed at a later time under additional permits