Hutto City Council voted unanimously for 2 miles of road reconstruction in parts of Old Town, CR 132 and the Carl Stern area.

The details

The $732,434 contract with Bennett Paving will reconstruct some city alleys and the following roads:
  • Carl Stern Drive
  • CR 132
  • Taylor Street
  • West Street
  • Anthony Street
  • Pecan Street
Due to poor pavement conditions, the roads will receive a 2-inch asphalt overlay for preservation and rebuilding. Other spot repairs will also occur during the project, as well as striping Carl Stern Drive.

This work is scheduled to wrap up by the end of September.

Some history


In May 2023, Hutto received an updated evaluation of pavement conditions, which also recommended a five-year street maintenance plan.