CR 132, from Branson Boulevard to CR 134 in Hutto, will experience traffic disruptions over the next few weeks while the city completes wastewater line construction.
The details
The construction project on CR 132, south of Hwy. 79, began March 17 to construct roughly 11,000 feat of wastewater line. Hutto anticipates the project to last three to four weeks, weather and other factors permitting, according to a city news release.
Work will take place Monday through Friday, from 9 a.m. to 4 p.m. until the project is complete.