Major road improvements are about to be underway or are continuing throughout Pflugerville in early December.

The following updates include information provided by the city.

1. Work on Grand Avenue Parkway is expected to begin Dec. 6.

During a Nov. 9 City Council meeting, officials approved a nearly $2.76 million bid from Terra Path Construction to take the project reins.

City documents state Grand Avenue Parkway was reconstructed in 2017 from Viki Lynn Place to Picadilly Drive, but the project resulted in numerous pavement failures and distress areas.


An April 2019 evaluation identified pavement conditions and root causes of the failures, and subsequently, in March, the city contracted with engineering firm Kimley Horn to redesign that portion of Grand Avenue Parkway.

City information states the project will involve two separate phases as part of its traffic control plan, and access to adjacent properties and businesses will be maintained at all times.

Timeline: Dec. 6, 2021-June 2022

Cost: $2.76 million


Funding source: city of Pflugerville

2. Improvements to the intersection at Heatherwilde Boulevard and Pecan Street are scheduled to begin Dec. 6.

The project will turn the existing median of Heatherwilde into a left-turn lane, both north and southbound, according to city information. Lanes closest to the medians will be closed during construction, which is expected to be complete in April.

Cost: $330,085.25


Timeline: Dec. 6, 2021-April 2022

Funding source: city of Pflugerville

3. Crews will continue working overnight at the intersection of Pecan Street and FM 685/Dessau Road from Dec. 5-8. City information states the work will include rolling lane closures, and staff recommend taking alternate routes to avoid construction.

Cost: $4.3 million


Timeline: March-December

Funding sources: U.S. Department of Commerce’s Economic Development Administration, the Texas Department of Transportation, the Pflugerville Community Development Corporation and the city of Pflugerville