Starbucks: Schultz Lane, Pflugerville
Type of work: new construction
Estimated cost: $650,000
Timeline: Jan. 1, 2023-May 1, 2023
Scope of work: construct Starbucks shell and site improvements; minimal electrical and plumbing included; site improvements include utilities, paving, sidewalks, parking and site signage
Camp Doublecreek: 3311 Kelly Lane, Pflugerville
Type of work: new construction
Estimated cost: $200,000
Timeline: Jan. 1, 2023-May 31, 2023
Scope of work: new youth day camp buildings
Hobby Lobby: Pflugerville
Type of work: new construction
Estimated cost: $4 million
Timeline: Jan. 16, 2023-Oct. 16, 2023
Scope of work: new building and site work
Editor’s Note: This commercial permit could not be mapped.
QuikTrip: 1105 Old Austin Hutto Road, Pflugerville
Type of work: new construction
Estimated cost: $475,000
Timeline: May 1, 2023-Dec. 1, 2023
Scope of work: the new construction of a convenience store with retail gasoline sales
Dick’s Sporting Goods: 19000 Limestone Commercial Drive, Ste. 200, Pflugerville
Type of work: renovation/alteration
Estimated cost: $250,000
Timeline: Jan. 29, 2023-March 1, 2023
Scope of work: renovation of a single-level Dick’s Sporting Goods retail space for the creation of a new footwear department and associated storage
Salad and Go: 130 Chris Kelley Blvd., Hutto
Type of work: new construction
Estimated cost: $300,000
Timeline: Jan. 30, 2023-April 28, 2023
Scope of work: ground-up
Marco’s Pizza: 6111 FM 1660, Ste. 300, Hutto
Type of work: renovation/alteration
Estimated cost: $215,000
Timeline: Nov. 15, 2022-Jan. 16, 2023
Scope of work: first-time interior alteration
Flooring Solutions: 134 TK Industrial Blvd., Hutto
Type of work: new construction
Estimated cost: $1.465 million
Timeline: Oct. 24, 2022-June 30, 2023
Scope of work: interior office finish-out in an existing single-story shell building; interior office area to be conditioned; warehouse area to be nonconditioned; mechanical equipment to be mounted on the roof
FM 1660 at Mager Lane improvements: intersection of FM 1660 and Mager Lane, Hutto
Type of work: renovation/alteration
Estimated cost: $2.41 million
Timeline: Oct. 3, 2022-July 31, 2023
Scope of work: proposed roadway widening, pedestrian facilities, drainage, signals, signing and pavement marking improvements
CRI Hutto-Office and Warehouse: Chandler Road and FM 1660, Hutto
Type of work: new construction
Estimated cost: $1.5 million
Timeline: Nov. 15, 2022-Nov. 15, 2023
Scope of work: new site work and construction of two metal buildings for offices and warehouse; interior space includes offices, a conference room, break room, restrooms, shower and production area