Graybar AUTX: 3212 E. Pecan St., Pflugerville
Type of work: renovation/alteration
Estimated cost: $4,507,200
Timeline: Oct. 1, 2022-March 31, 2023
Scope of work: Tenant improvement project for Graybar Electric. The project is a 102,060-square-foot facility that includes 2,874 square feet of office space and 99,186 square feet of warehouse
Residence Inn: East Pecan Street and Impact Way, Pflugerville
Type of work: new construction
Estimated cost: $25 million
Timeline: Feb. 28, 2023-Aug. 31, 2024
Scope of work: five-story, extended-stay hotel
Church of the Harvest: 202 Meadow Lane, Pflugerville
Type of work: new construction
Estimated cost: $2 million
Timeline: Sept. 1, 2022-July 31, 2023
Scope of work: new church building
Liquor Store: 1300 W. Pflugerville Parkway, Ste. 340, Pflugerville
Type of work: additions to existing building
Estimated cost: $80,000
Timeline: Sept 12-Dec. 19
Scope of work: 1,750-square-foot liquor store going into an existing retail center
Picadilly Retail Center II: 428 Grand Avenue Parkway, Pflugerville
Type of work: new construction
Estimated cost: $750,000
Timeline: Nov. 11, 2022-May 31, 2023
Scope of work: new warm shell building intended for retail; the project is a single story
Gattis School Medical Plaza: 201 CR 138, Hutto
Type of work: new construction
Estimated cost: $5.5 million
Timeline: Oct. 1, 2022-June 30, 2023
Scope of work: two-story medical office building with lobby and core restrooms built out and tenant shell space to be built out in a future project
Texas Urgent Care: 440 Chris Kelly Blvd., Hutto
Type of work: new construction
Estimated cost: $750,000
Timeline: Aug. 22-Oct. 31
Scope of work: new construction of an urgent care clinic of approximately 3,000 square feet; included will be a lobby, accessible restrooms, exam rooms and a lab area; also included will be site improvements such as parking, drives and sidewalks
H-E-B Hutto C-Store: 5008 Gattis School Road, Hutto
Type of work: renovation/alteration
Estimated cost: $1.2 million
Timeline: Jan. 4, 2022-July 7, 2023
Scope of work: remodel of existing building
Schenker: 600 Schneider Blvd., Hutto
Type of work: renovation/alteration
Estimated cost: $2.3 million
Timeline: Aug. 25-Dec. 31
Scope of work: build-out for existing warehouse/office space
Viahart’s Warehouse: 5920 Chandler Road, Bldg. A, Ste. 200, Hutto
Type of work: new construction
Estimated cost: $1.5 million
Timeline: Sept. 1, 2022-Jan. 31, 2023
Scope of work: construction of a new warehouse