Central Texas toll agency settles dispute with MoPac contractor, will pay $21.5M

Drone footage from the Central Texas Regional Mobility Authority shows the nearly complete northbound express lane near downtown Austin in September.

Drone footage from the Central Texas Regional Mobility Authority shows the nearly complete northbound express lane near downtown Austin in September.

The Central Texas Regional Mobility Authority has agreed to pay the MoPac contractor $21.5 million to settle disputes over issues that led to the project’s two-year delay.

The agency’s board approved the amount Tuesday with CH2M, which alleged the Mobility Authority owed it a total of $113 million because of issues, such as unknown underground utilities, hard rock and inclement weather.

The MoPac Improvement Project is adding one express toll lane to MoPac in each direction from Parmer Lane to Cesar Chavez Street.

In October 2016, the Mobility Authority opened part of the northbound express lane from RM 2222 to Parmer. It is anticipating opening the rest of the northbound lane from Cesar Chavez to RM 2222 as early as Sept. 30 or in early October. The southbound lane would open at a later date.



“This settlement ensures that all future claims are off the table, avoiding a lengthy and costly court process,” said Jeff Dailey, the Mobility Authority’s deputy executive director, in a statement released Tuesday morning.

However, the Mobility Authority will only have to pay the amount if CH2M meets a new set of project milestones. In accepting the settlement, the contractor has agreed to complete the full project, including the southbound express lane, by Oct. 27. CH2M faces a loss of $50,000-$100,000 per day if it does not meet that milestone.

“The Mobility Authority’s top priority is opening the full project as soon as possible, and we’re confident this course of action will help achieve that goal,” Dailey said. “We believe the MoPac Improvement Project is an investment that will benefit Central Texans for decades to come, and that is a win for the community.”

The agency also reported that payment of the $21.5 million will not affect toll rates, which are based on the speed and traffic volume of vehicles in both the express toll lane and main lanes. The price goes up when traffic increases to keep traffic flowing.

The amount the Mobility Authority would pay to CH2M is separate from the $20 million CH2M has already accrued in liquidated damages because of the project being two years late.

In December 2015, the Mobility Authority issued a notice of default against CH2M because of those delays. However, the toll agency opted not to proceed with the default and instead continue with dispute resolution to settle ongoing issues related to the delays.

CH2M has previously stated it has lost about $66 million because of the MoPac project delays and opted in January to subcontract the remainder of the project to Lane Construction.
By Amy Denney

Managing Editor, Austin metro

Amy has worked for Community Impact Newspaper since September 2010, serving as reporter and later senior editor for the Northwest Austin edition as well as covering transportation in the Austin metro. She is now managing editor for the 10 publications in the Central Texas area from Georgetown to New Braunfels.



MOST RECENT

Brandon Cardwell, the district's executive director of facilities and construction, addressed the PfISD board during an Oct. 21 meeting. (Brian Rash/Community Impact Newspaper)
Bohls Middle School within PfISD slated for late December completion

Brandon Cardwell, the district's executive director of facilities and construction, said during the district's Oct. 21 board meeting that much work is still needed on the campus, but he is encouraged by the pace at which crews are operating.

North Austin home under construction
Homes prices across Northwest Austin fall for third straight month

The median home price in Northwest Austin dropped to its lowest figure since March 2021.

Cumby Group is planning development for three adjacent multifamily projects on Manor Road in East Austin, including The Emma apartments. (Courtesy Cumby Group)
3 years in, Austin is falling behind on goals in affordable housing plan

From 2018-20, the city only reached 12% of its 10-year goal to build thousands of new homes and rental units.

Taco Palenque is now open as drive-thru only in Round Rock. (Brooke Sjoberg/Community Impact Newspaper)
CI NATION ROUNDUP: Taco Palenque opens in Round Rock; Plano ISD considering two draft calendars for 2022-23 school year and more top news

Take a look at the top five trending stories across all of Community Impact Newspaper’s coverage areas as of Oct. 21.

The Austin Transit Partnership is exploring above- and below-ground options for a transit center at the East Riverside Drive and South Pleasant Valley intersection. (Courtesy Austin Transit Partnership)
Project Connect plans to explore above-, below-ground options for East Riverside/Pleasant Valley Transit Center

After hosting a community design workshop, the group overseeing Project Connect designs is moving forward with options for both an underground and above-ground station at the intersection.

Medici Roasting
Local coffee chain Medici Roasting opens cafe in The Domain

Medici Roasting is now open in The Domain inside the Flatiron Domain building.

A calculator created by the Rocky Mountain Institute looks at the environmental impact of TxDOT's proposed designs for I-35 in Central Austin, one of the most congested roadways in the country. (Benton Graham/Community Impact Newspaper)
Nonprofit's tool says TxDOT I-35 expansion proposals would have profound environmental consequences

The tool says that the proposal would create between 255 and 382 million additional vehicle miles traveled per year.

Photo of the Travis County administration building and sign
Travis County hears update on process to reassess master plan for aging correctional facilities

The process comes after county commissioners opted to pause all activities of the master plan over the summer.

Rodeo stock image
Inaugural Williamson County Fair and Rodeo ready to open gates Oct. 21 after coronavirus delay

After the inaugural Williamson County Fair and Rodeo was postponed in 2020, county and fair officials said they are excited to kick off the agricultural celebration.

Renderings of the conceptual tower were shown depicting a roughly 100-foot tower, but the intent is to build a smaller tower. A total of $2.43 million was given as an estimated cost for a 100-foot gravity tower, but presenters said the cost would scale down with a smaller tower. (Courtesy city of Frisco)
CI NATION ROUNDUP: Early concept for Frisco’s Northwest Community Park includes biking tower for ‘gravity riding’; Perky Beans Cafe now open in Leander, and more top news

Take a look at the top five trending stories across all of Community Impact Newspaper’s coverage areas as of Oct. 20.

Austin Cultural Arts Division staff provided an update on several funding opportunities for the creative sector Oct. 18. (Screenshot via city of Austin)
Austin's arts community could be in line for millions more in relief dollars this year

Additional relief for artists may be available in the coming months, while a broader review of the city's cultural funding opportunities continues.