1. Dedicated left-turn lane
Construction will finish in late December on a left-turn lane into the Austin Board of Realtors’ property at 4800 Spicewood Springs Road and other drainage upgrades. ABoR is contributing $310,864 toward the project, which aims to relieve congestion on the two-lane roadway.
Timeline: October-December Cost: $440,942 Funding sources: ABoR, city of Austin
2. US 183 frontage roads
The Texas Department of Transportation will resurface the US 183 frontage roads from Anderson Mill Road to McNeil Drive.
Timeline: spring-early summer Cost: $2 million Funding sources: state funds
MoPac construction[/caption]3. MoPac construction
In December crews are pouring concrete for the southbound express lane underpass. On the northbound side near Cesar Chavez and Sixth streets, work continues to pave the new ramp where traffic will shift in mid- to late January and when main lanes will be reduced to two lanes.
Timeline: October 2013-late 2016 Cost: $204 million Funding sources: state and federal
4. Parmer Lane resurfacing
TxDOT is seeking bids in December on a project to repair and resurface Parmer Lane from SH 45 N to the Travis County line just north of McNeil Drive.
Timeline: summer 2016 (construction) Cost: $3.3 million Funding sources: TxDOT
5. Trail construction
Construction on the Northern Walnut Creek Trail (A) Phase 1A, which includes a redesign of about a half mile of trail from Amherst Drive near Balcones District Park to MoPac, will begin in the summer on the southern end. Construction on the northern end will start in 2017. Work on (B) Phase 1, a 2.5-mile-long trail segment from MoPac to Walnut Creek Metropolitan Park, will be substantially complete in early 2016.
Timeline: March 2013-early 2016 (Phase 1), summer 2016-2018 (Phase 1A) Cost: $5.5 million Funding sources: city of Austin bonds
6. Trail planning
The second phase of the Northern Walnut Creek Trail will be 1.8 miles long from the Walnut Creek park to I-35 at Walnut Creek. The project is under design, and the city will hold another public meeting in early 2016.
Timeline: TBD Cost: TBD Funding sources: TBD