From Aug. 15-17, the inside eastbound lane of Common Street will be closed to replace a valve located at the intersection of Common Street and Central Avenue. The constriction will be completed by New Braunfels Utilities contractor MGC as part of the city of New Braunfels' citywide roadway project.
According to NBU officials, the East South Street and South Central Avenue water line realignment project is relocating and replacing approximately 900 linear feet of the existing 6-inch water line between South Union Avenue and South Houston Avenue with an 8-inch water line. The project will relocate approximately 100 linear feet of the existing 8-inch water line from the East South Street intersection toward Common Street.
Up-to-date traffic impacts for NBU projects can be found at http://nbutexas.com/current-construction-impacts-and-road-closures, or on the NBU Facebook and Twitter social media channels.