Read about these projects and more below. This list is not comprehensive.
Upcoming projects
Williams Drive
Project: Construct medians with turn lanes on Williams Drive from I-35 to Serenada Drive, including a shared-use path on the north side of Williams Drive, a new waterline, and street lighting from DB Wood Road to Jim Hogg Road to and Serenada Drive to I-35
Update: In the design phase, with the first phase of the project—street lighting from DB Wood to Jim Hogg—anticipated to begin in the spring
- Timeline: 2023-27
- Cost: $18.6 million
- Funding sources: city of Georgetown, traffic impact fees, federal grants, tax increment financing
Project: Widen 2.91 miles of SE Inner Loop to a four-lane, divided road from Hwy. 29 to FM 1460, and add a shared-use path for pedestrians and bicycles on one side
Update: In the design phase, with real estate acquisition and utility relocation ongoing
- Timeline: 2022-28
- Cost: $70.6 million
- Funding sources: city of Georgetown, Georgetown Transportation Enhancement Corporation
Project: Construct additional travel lanes, lengthen turn lanes and improve traffic signals on Hwy. 29 from Wolf Ranch Parkway to I-35 as well as add shared-use paths
Update: Construction is expected to begin in the spring
- Timeline: 2023-27
- Cost: $10.1 million
- Funding source: Georgetown Transportation Enhancement Corporation
Project: Construct two pedestrian and bicycle bridges crossing the San Gabriel River, adjacent to the existing Austin Avenue bridges
Update: A redesign for the project was approved at a Dec. 9 council work session due to cost increases associated with the original design
- Timeline: 2023-TBD
- Cost: $21 million
- Funding sources: city of Georgetown, developer fees
Project: Widen Shell Road from Williams Drive to Sycamore Street to four lanes with a raised median, shared-use path, and left- and right-turn lanes
Update: Utility relocations are ongoing and construction is expected to begin in mid-2026
- Timeline: 2022-27
- Cost: $21.17 million
- Funding source: city of Georgetown
Southwestern Boulevard
Project: Reconstruct and expand Southwestern Boulevard to two lanes with a center turn lane and other improvements from University Park to SE Inner loop
Update: Substantial completion expected by the end of February
- Timeline: 2020-26
- Cost: $6.58 million
- Funding source: city of Georgetown, Williamson County
Project: Upgrade Rockride Lane to a two-lane collector roadway with a continuous center left-turn lane and a 10-foot-wide shared-use path along one side from SE Inner Loop to Sam Houston Avenue
Update: The first phase of the project, from SE Inner Loop to Mitchell Elementary and Wagner Middle schools, was substantially completed last fall. Construction continues with estimated completion by September
- Timeline: 2022-26
- Cost: $12 million
- Funding source: city of Georgetown
Project: Add four 12-foot wide lanes, a center turn lane and a shared-use path from Hwy. 29 to Oak Ridge Road
Update: All four lanes are set to be open to traffic by March 31, with project completion in July
- Timeline: 2023-26
- Cost: $29.6 million
- Funding source: city of Georgetown

