City officials said Phase 2 of the San Gabriel Parkway project, which will connect San Gabriel to Ronald Reagan Boulevard, has been paused due to the city prioritizing water infrastructure.
Construction on a water tower adjacent to the Phase 2 right of way will run from April 2023-summer 2024. Subsequently, work on the extension will take place from winter 2024 to summer 2025.
The $7.6 million road project funded by the city is intended to provide residents in Palmera Ridge and Palmera Bluff access to Ronald Reagan.