Shenandoah City Council continued discussions regarding the city’s 2021-22 capital improvement plan during an April 28 meeting.
Shenandoah Public Works Director Joseph Peart presented several changes to the plan, noting the priority of some improvements had been moved around due to cost estimates and how vital they are to be completed.
Among the changes is work on the city’s wastewater treatment plant, which Peart said the plan is to lump in additional improvements for security cameras and replacement fencing so it is one project. Information from the capital improvement plan estimates this will cost around $77,000 for the additions.
City Council member Ron Raymaker noted the city's inflow and infiltration testing had been moved to a low-priority item out of the improvement plan and expressed concerns about it being pushed back another year.