Oak Ridge North City Council approved a $63,558 payment to CSB Contractors to begin architecture and construction on the new building for the city Public Works and Police departments at the council's Oct. 23 meeting.
What you need to know
As part of the city's Robinson Road realignment and central Plaza District plans, City Council approved one of the first payments to CSB Contractors for the construction of the relocated public works and police department building. The facility is moving from Robinson Road to Spectrum Way.
Public Works Director James Corn said during the meeting clearing work on the new site was 75% complete, and the contractors wanted to begin ordering materials needed for the project to prevent delays.