A presentation at the Feb. 17 Conroe ISD board of trustees meeting covered ongoing and future projects throughout the district.
What to know
Easy Foster, Conroe ISD's executive director of planning and construction, presented an overview of the 2023 bond projects, including the following:
- Proposed contracts: 37
- Completed projects: 8
- Projects under construction: 20
- Projects currently in the design process: 4
- Projects to begin design phase: 5
CISD voters passed a $1.8 billion bond package in 2023, as previously reported by
Community Impact.
The update
Conroe High School renovations
- Project: The school is making improvements to its campus to accommodate student growth.
- Update: The district is currently working on the front entry and the auditorium, Foster said.
- Location: 3200 W. Davis St., Conroe
- Timeline: completion anticipated this year
Janene Fowler Intermediate School- Project: This campus, serving fifth and sixth grades, will serve the Conroe and Timber Mill feeder zones.
- Update: Construction is underway on the building, along with permits being completed by the city of Conroe to receive electricity and water, Foster said.
- Location: FM 1314 north of Crighton/Creighton Road, Conroe
- Timeline: opening in August
Kacy Arnold Elementary School- Project: This new elementary school will be located in the Grand Oaks High School feeder zone.
- Update: The building will be completed in May, and the district will be able to move in during the summer, Foster said.
- Location: 28378 Sterling Oak Drive, Spring
- Timeline: opening in August
Grand Oaks Junior High School and Ninth Grade Campus- Project: The new school will serve seventh, eighth and ninth grades in the Grand Oaks High School feeder zone.
- Update: Construction is underway on the building, Foster said.
- Location: 28075 Woodson’s Grand Drive, Spring
- Timeline: opening in January 2027
Timber Mill High School- Project: Timber Mill High School will create a new feeder zone with students from Conroe and Caney Creek high schools.
- Update: Construction is on schedule as asphalt for the athletic track has been set, Foster said.
- Location: 2700 N. Loop 336 E., Conroe
- Timeline: opening in August 2027
Lynn Cartwright Junior High School- Project: Serving fifth and sixth grades, this campus will serve the Conroe High School feeder zone.
- Update: The construction process was on schedule, and the roof is being set in, Foster said.
- Location: FM 1314 north of Crighton Road, Conroe
- Timeline: opening in August 2027
Caney Creek High School ninth-grade campus- Project: The ninth-grade campus will have a capacity of 1,600 students.
- Update: The district has been working with a private utility company and a road is being made for a water tower to be made to connect to the building, Foster said.
- Location: FM 1485 just north of Hwy. 242
- Timeline: opening in August 2027