Harris County Flood Control District officials hosted a groundbreaking ceremony March 10 for two projects in the Spring area of the Cypress Creek watershed.
According to a March 7 news release, the first project will include the construction of a stormwater detention basin on a 6.81-acre site near the junction of Lemm Gully and Wunsche Gully, located just north of Cypresswood Drive between I-45 and the Hardy Toll Road.
According to the release, the HCFCD contributed approximately $777,000 in 2018 flood bond funds toward the project with project partner Harris County Municipal Utility District No. 249 spending more than $610,000 to purchase right of way and nearly $165,000 to fund design, construction and additional right of way.
Upon completion, the basin will be able to hold roughly 37 acre-feet, or more than 12 million gallons, of stormwater during heavy rain events. The project is being managed by Harris County MUD 249.