Hamilton Pool Road updates
Work to improve Hamilton Pool Road from RM 12 to Hwy. 71—including adding a continuous turning lane, shoulders on both sides of the road, dedicated turning lanes and new travel lanes in each direction—will continue in 2023. The right side of the roadway has been prepared by crews, and portions on the left side will begin in early 2023, along with drainage projects.
- Timeline: December 2021-spring 2023
- Cost: $16 million
- Funding source: Texas Department of Transportation
William Cannon improvements