From renovations to new schools, check out eight of the ongoing and recently completed bond-funded projects in Hays CISD.
1. Lehman High School Auditorium
- Schedule: August 2023-January 2026
- Scope of work: added an 800-seat auditorium, scene shop, two classrooms, and storage for fine arts program rehearsals and performances
- Status: 100%
- Cost: $53.1 million
- Funded by Proposition B of the 2023 bond
2. Elementary school No. 18 design
- Schedule: March-August 2026
- Scope of work: designs the district’s eighteenth elementary school, which will accommodate 900 students
- Status: 10% complete
- Cost: $4.2 million
- Funded by Proposition A of the 2023 bond
3. Fine Arts and Athletic Multipurpose Activity Centers