Four road projects have been recently completed or are underway in the Northeast San Antonio Metrocom. Here’s the latest:

Ongoing projects

FM 2252 reconstruction

Project:
The reconstruction of FM 2252 from Evans Road to FM 3009 will see the expansion of the roadway from two to four lanes with bike lanes and sidewalks.

Update: While road work is underway, alternating lane closures will be scheduled, limiting sections of the road to one lane. During these closures, traffic will be directed or detoured.
  • Timeline: Jan. 15 2024-2027
  • Cost: $48.5 million
  • Funding source: Texas Department of Transportation
Bolton Road reconstruction


Project: The Bolton Road Reconstruction project focuses on the section of roadway from Haeckerville road to Stolte Road. The project funding is split between the city of Cibolo and Guadalupe County.

Update: The portion of Bolton Road from Zuehl Road to Stolte Road was closed to through traffic. Zuehl Road was also closed to through traffic. The project is in the final phase of construction.
  • Timeline: Jan. 29-May
  • Cost: $1.55 million
  • Funding sources: city of Cibolo CO bonds, Guadalupe County
Haeckerville Road reconstruction

Project: The Town Creek Drainage and Haeckerville Road Reconstruction projects included drainage improvements and the construction of a new bridge on Haeckerville Road. The road was also widened to include sidewalks, curbs, bike lanes and two travel lanes.

Update: The final phase is under construction with an expectation of the drainage/road project being complete by early June.
  • Timeline: 2022-June 2024
  • Cost: $8.75 million
  • Funding source: GO bonds, drainage impact fees, water impact fees, street impact fees
Completed projects


Dean Road reconstruction


Project: Dean Road was reconstructed from Old Wiederstein Road to Green Valley Road. The reconstruction project is one of three road reconstructions between the city of Cibolo and Guadalupe County.

Update: In March, the second phase of the project began, limiting the road traffic. Since the start of the second phase, the contractor has worked on finalizing the road construction, which was completed May 9.
  • Timeline: Jan. 29-May 9
  • Cost: $1.28 million
  • Funding source: city of Cibolo CO bonds, Guadalupe County