From street repairs to widening thoroughfares, the following is a list of the latest updates on road work in New Braunfels.
Completed projects
Altgelt Lane repairs
Update: The project was recently finished.
- Timeline: January 2024–March 2024
- Cost: $300,000
- Funding source: 2023 bond citywide streets program
Project: A mill and overlay with spot base repair and striping work was scheduled on Hunter Road from FM 306 to Gruene Road.
Update: The project was recently completed.
- Timeline: January 2024–April 2024
- Cost: $400,000
- Funding source: 2023 bond citywide streets program
Ongoing projects
Klein Road widening
Update: The project is ongoing as construction continues and on track to be complete.
- Timeline: May 2023-fall 2024
- Cost: $17.5 million
- Funding source: 2019 Bond
Project: The city is installing new signals and making intersection improvements at County Line Road at FM 1044, Schmidt Avenue at FM 1044, and Klein Road at Klein Way.
Update: The city is nearing completion on the installations.
- Timeline: 2022-summer 2024
- Cost: $1 million
- Funding source: Roadway Impact Fees from Service Area 5
South Union Avenue improvements
Project: There will be roadway rehabilitation from Common Street to Garden Avenue, which will include pedestrian and intersection improvements.
Update: The project design is nearing completion and construction is to begin soon.
- Timeline: Bidding later this summer, construction fall 2024–TBD
- Cost: $2.5 million
- Funding source: 2023 bond citywide streets program
McQueeney Road repairs
Project: The project's scope is to rehabilitate McQueeney Road from County Line Road to I-35 frontage road, including a mill and overlay, base repair and sidewalk completion within project limits.
Update: Construction for the project is scheduled to begin soon.
- Timeline: Fall 2024–TBD
- Cost: $2.0 million
- Funding source: 2023 bond citywide streets program
Project: Planning is complete for the reconstruction of Goodwin Lane from FM 306 to Conrads Lane and Conrads Lane from Goodwin Lane to the I-35 frontage road. The project includes roadway expansion, drainage improvements, bridge construction and the addition of sidewalks and a shared-use path.
Update: Planning is complete for the project and construction will begin in the fall.
- Timeline: Fall 2024–2026
- Cost: $24.2 million
- Funding source: 2019 Bond