SH 130 widening
Crews are widening existing main lanes and bridges of SH 130 to add a third lane in both northbound and southbound directions between SH 45 N. and Hwy. 290 E.
Status: the third lane from Hwy. 290 to Cameron Road is currently open in both directions; contractor is performing final striping, structural painting and other corrective work in the area; excavation operations are underway from Cameron Road to SH 45 N; drilling crews began working on drill shafts at Cameron Road in early January to widen the bridge structure