Athletic locker expansions, an inclusive playground and a roof replacement are among the facility improvements and infrastructure needs discussed during Friendswood ISD’s board of trustees' Nov. 16 workshop.
Budget explained
FISD’s 2026 bond program includes $25 million for districtwide priority maintenance. Of that amount, nearly $1.8 million has been allocated to new school buses, leaving around $23 million for other infrastructure needs, FISD’s Chief Financial Officer Amber Petree said.
Other bond allocations include around:
The district has around $4 million remaining in its 2020 bond program, which is designated for critical infrastructure projects, Petree said.
The district also has nearly $2.2 million available through its capital projects fund to support additional campus improvements, including athletics-related needs that were not outlined in the 2026 bond.
Zooming in
The 2026 bond program will fund science lab renovations at Bales Intermediate and Windsong Elementary, converting existing classrooms into dedicated science learning spaces, including additional instructional and storage space, laboratory sinks and magnetic writable wall surfaces.
Other maintenance needs include erosion beneath sidewalks and sloping in the band room at Friendswood Junior High. At Friendswood High School, planned improvements include bathroom renovations, flooring replacements and waterline upgrades, including replacement of the school's main waterline, documents show.
The district also plans to replace the roof at the administration building, documents show.
What’s new
Working with campus leadership, the district identified several additional projects through its capital projects fund, including:
Westwood Elementary: Redesigning the library after mold damage over the summer required the removal of many of its existing materials. The district is also exploring an upgrade to the prekindergarten playground behind the gym, with swing sets and inclusive, ADA-compliant equipment designed for younger students.
Friendswood High School: Expanding athletic locker space by reconfiguring existing facilities to provide lockers to athletes while their respective sports are in season.
Other improvements include HVAC and mechanical upgrades, fire alarm systems and security enhancements, documents show.
One more thing
The board also tabled a nearly $175,000 proposal for geotechnical engineering services for the career and agricultural sciences center, opting to explore more affordable options.
The proposed work includes a geological fault study, soil borings, groundwater measurements and laboratory testing, documents show.
Looking ahead
District officials will continue evaluating project scopes, costs and funding options before bringing recommendations to the board, documents show.