The renovation and expansion of the school is a part of the district’s $380.1 million bond that addresses AISD’s enrollment growth. (Rendering courtesy PBK Architects)
A new career and technical education, or CTE, building is among some of the additions included in Alvin High School’s renovation and expansion project.
Officials with Houston-based PBK Architects reviewed its schematic design for the high school’s renovation and expansion project at Alvin ISD’s board of trustees’ Oct. 21 meeting.
The project
The renovation and expansion of the school is a part of the district’s $380.1 million bond that addresses AISD’s enrollment growth. The bond passed in November 2024, Community Impactpreviously reported.
According to a presentation by PBK Architects, some of the following will be built for the renovation and expansion:
New CTE building, which will replace the Luke Kennedy Vocational Building and includes a wing that will connect to the cafeteria
Dining expansion, which will allow an indirect capacity of 108 students for larger lunch areas in conditioned spaces
Large group instructional spaces for day-to-day student activities
The new CTE building will be a facility that allows students to specialize in some of the following programs:
Advanced technology, manufacturing and engineering center
Floral
Robotics
Health care
(Courtesy PBK Architects)
The details
The renovation and expansion project for AHS is slated to cost nearly $100 million, according to bond documents.
Other items for the renovation and expansion of the school include:
Additional student capacity for 400-500 students
Repurpose historic auditorium space as the campus front entrance
Enhanced campus security
Removal of older temporary buildings
The timeline
While an updated timeline was not disclosed at the meeting, the renovation and expansion of AHS is slated to complete toward mid-to-late 2031, according to bond documents.
According to bond documents, the school will undergo the following timeline:
July 2026-February 2027: geotechnical and drainage study
March-December 2027: design
January-April 2028: bid and permit
May 2028-February 2031: construction
March-June 2031: move in
July 2031: opens
August-October 2031: close out