1. Intersection improvements
In July, the city of Austin installed two pedestrian hybrid beacons at North Lamar Boulevard and Rundberg Lane and in front of John B. Connally High School. The city also installed in July a traffic signal on Lamar north of Parmer Lane. The projects are part of an initiative to upgrade five intersections prioritized for safety improvements. Other projects on Lamar at Parmer and Rundberg include constructing raised medians and raised right-turn channelized islands, restriping and adding crosswalks. Timeline: July-December Cost: $1.8 million Funding sources: city of Austin,Texas Department of Transportation
2. MoPac frontage roads resurfacing
In August, TxDOT completed a resurfacing project on the MoPac frontage roads from Parmer Lane to Waters Park Road. Timeline: June-August Cost: $787,600 Funding sources: TxDOT
3. I-35 main lanes repaving
TxDOT will resurface the I-35 main lanes from Wells Branch Parkway to Rundberg Lane. The project will be bid upon in November. Timeline: TBD Cost: estimated at $4 million Funding sources: TxDOT
4. New sidewalks near Barrington Elementary School
As part of the city of Austin’s Quarter Cent Fund program, the city will build sidewalks near Barrington Elementary School in North Austin on Shepard Drive, North Drive, East Fawnridge Drive and Carpenter Avenue. Funding for the QCF comes from Capital Metro revenue originally slated to go toward light rail in 2000. Projects funded by the QCF are located within 1/4 mile of a school and transit stop and are designed to enhance safety, provide access to schools and support transit. Timeline: September-December Cost: $370,000 Funding sources: city of Austin, Capital Metro