1. Harris County Precinct 1 is widening Walters Road between FM 1960 and Old Walters Road from two to four lanes as well as installing a new traffic signal and a left-turn lane at Bammel North Houston Road. The cost of the project is $11 million.
    Estimated timeline: April 2017-September 2018


2. Allgood Construction began work on a Harris County Precinct 4 project in January. The $4.8 million project  will widen the two-lane asphalt roadway at Hufsmith-Kohrville Road Segment 6, which extends from Mahaffey Road to FM 2920, to four concrete lanes. The project is slated for completion in December.
Estimated timeline: Jan. 29-Dec. 24

3. Allgood Construction is expected to complete construction in August 2019 on a $9.4 million project to widen the Gosling Road bridge across Willow Creek and upgrade the two-lane asphalt road to four concrete lanes between West Mossy Oaks and West Rayford roads in Spring.
Estimated timeline: March 21-August 2019

4. The portion of Texas Department of Transportation’s $2.3 million Statewide Curb Ramp Project on FM 1960, implemented to meet Americans with Disabilities Act requirements, has been delayed by utility conflicts, TxDOT Public Information Officer Danny Perez said. The project is expected to resume in August.
Estimated timeline: Oct. 2016-early 2019