This Sugar Land project is 90 percent complete, and work crews continue to pave the streets where new storm sewer improvements were made. This project is slated to finish approximately one month ahead of schedule. Timeline: May 2017-February 2018 Cost: $3.2 million Funding source: city of Sugar Land