Conroe | Montgomery May 2017 ongoing projectsFM 1097 widening

The Texas Department of Transportation is expanding FM 1097 between I-45 and Hwy. 75 from two to four lanes and adding a left-turn lane. Construction is about 79 percent complete. Timeline: July 11, 2016-third quarter 2017 Cost: $3.5 million Funding sources: TxDOT

FM 1488 expansion, overpass

A widening project to expand FM 1488 from two to four lanes between FM 149 and Community Road has reached 69 percent completion. The project also includes construction of a railroad overpass on FM 1488 at the FM 149 intersection over the Burlington Northern Santa Fe railroad tracks. Timeline: Oct. 21, 2015-fourth quarter 2017 Cost: $27.6 million Funding sources: TxDOT

FM 149 widening

TxDOT will widen FM 149 in Montgomery by the end of the year. The project will add a center left-turn lane and span from FM 1097 to Hwy. 105. Timeline: scheduled for fourth quarter 2017 Cost: TBD Funding sources: TxDOT

FM 149 repairs

TxDOT sent a repair project out to bid for FM 149. The project will repair the base of a segment of roadway between the south Montgomery city limits to Keenan Cut Off Road. Timeline: mid-2017-2018 Cost: $2.86 million Funding sources: TxDOT

FM 3083 railroad overpass

TxDOT has undertaken a project that will widen FM 3083 from two to four lanes and build a bridge over the Union Pacific Corp. railroad tracks east of Hwy. 75. The agency has already widened FM 3083 in a separate project from I-45 to the starting location of the overpass bridge. The project has reached 37 percent completion and is expected to take about two years to finish. Timeline: May 2016-third quarter 2018 Cost: $13.1 million Funding sources: TxDOT

Hwy. 105 improvement project

The city of Conroe started construction on a Hwy. 105 improvement project Oct. 10. The project is 52 percent complete and will add a raised median throughout the roadway from I-45 to Frazier Street. The median will limit left-hand turns to designated intersections for transit safety purposes. Construction includes sidewalks on each side of the roadway. 5 Oct. 10, 2016-first quarter 2018 Cost: $3.5 million Funding sources: city of Conroe, TxDOT   Conroe | Montgomery May 2017 ongoing projects