Check out five upcoming and ongoing road projects in Dallas-Fort Worth.
Upcoming projects
1. Legacy Drive widening
Project: The project will build two lanes of Legacy Drive from Prosper Trail to a future Prosper ISD middle school, widen the roadway to four lanes near the school and construct a water line.
Update: Prosper Town Council approved a $6.1 million construction contract for the project at a May 19 meeting, and construction is expected to begin later this summer.
- Timeline: summer 2026-summer 2027
- Cost: $10.6 million
- Funding source: city of Prosper, Prosper ISD
Ongoing projects2. McKinney concrete panel replacement
Project: McKinney’s Roadstock project will replace damaged concrete panels and restripe Eldorado Parkway and Virginia Parkway.
Update: McKinney City Council approved an additional $1.2 million for the project at a May 5 meeting, and concrete panel replacement has started along Virginia Parkway.
- Timeline: estimated completion TBD
- Cost: $6 million
- Funding source: city of McKinney
3. Custer Parkway reconstructionProject: Custer Parkway will undergo street reconstruction from Campbell Road to Renner Road and street panel replacement from Renner Road to SH 190.
Update: Pavement replacements on multiple segments are underway, with several replacements expected to be complete in June.
- Timeline: fall 2024-fall 2026
- Cost: $23.1 million
- Funding source: city of Richardson
4. Keller Hicks Road improvementsProject: The project involves installing a three-lane undivided concrete pavement section from Park Vista Boulevard to Lauren Way and adding streetlights, sidewalks and stormwater drainage improvements.
Update: Keller Hicks Road has been reduced to one-way eastbound traffic from Park Vista Boulevard to Lauren Way for paving, which is expected to wrap up in early fall.
- Timeline: expected completion spring 2027
- Cost: $24 million
- Funding source: cities of Fort Worth, Keller
5. North Carroll Avenue improvementsProject: Construction will add turn lanes and made intersection improvements from Main Street to SH 114 access roads across six phases.
Update: Most construction is complete, and crews are wrapping up work on traffic signals and signs.
- Timeline: July 2025-summer 2026
- Cost: $2.1 million
- Funding source: city of Southlake, Texas Department of Transportation