Check out four transportation updates in Richardson for June.
Ongoing projects
1. Custer Parkway reconstruction
Project: Street reconstruction of Custer Parkway from Campbell Road to Renner Road and street panel replacement from Renner Road to State Highway 190.
Update: Pavement replacements on multiple segments, with several replacements expected to be complete in June.
- Timeline: fall 2024-fall 2026
- Cost: $23.1 million
- Funding source: city of Richardson
2. Richland Park Drive reconstruction
Project: This project consists of street reconstruction of Richland Park Drive from Sheffield Drive to Tiffany Drive and from Stillmeadow Drive to Wentworth Drive.
Update: The first phase of construction, sewer installation, is ongoing and expected to continue through May.
- Timeline: winter 2026-fall 2026
- Cost: $2.8 million
- Funding source: city of Richardson
3. West Shore Drive improvements
Project: Work includes pavement, sidewalk and utility improvements on West Shore Drive from Campbell Road to Arapaho Road and on Fontana Avenue from West Shore to Meadow View Drive.
Update: Sewer line replacement from Wisteria Way to Woodland Way is ongoing. Southbound lanes on that segment of West Shore Drive are temporarily closed.
- Timeline: fall 2025-summer 2027
- Cost: $10.4 million
- Funding source: city of Richardson
Upcoming projects
4. US 75 at Arapaho Road crossing enhancements
Project: Work will include Arapaho Trail improvements, pedestrian lighting, new ramps, a DART bus stop connection and a trail connection under US 75 with a barrier wall between a relocated U-turn lane.
Update: The project is currently under final design.
- Timeline: fall 2026-winter 2027
- Cost: $4.9 million
- Funding source: city of Richardson