[caption id="attachment_207908" align="alignright" width="218"]
Phase 1 Westpark Tollway extension/FM 1093 widening[/caption]
1. Phase 1 Westpark Tollway extension/FM 1093 widening
FM 1093 will be a two-lane frontage road in each direction on either side of the Westpark Tollway. The Westpark Tollway will be extended 2.3 miles west from the Grand Parkway and will be four lanes of concrete-paved highway with two lanes in each direction. An overpass will be built above the intersection of Katy-Gaston Road and Spring Green Boulevard.
Timeline: February 2016-February 2018 Cost: $63.9 million Funding sources: Fort Bend County Assistance District 1, Fort Bend County Toll Road Authority, Emergency Services District 100, Texas Department of Transportation.
[caption id="attachment_207905" align="alignright" width="194"]
Katy-Gaston Road realignment at FM 1093[/caption]
2. Katy-Gaston Road realignment at FM 1093
Katy-Gaston Road will be widened and realigned along a 0.5-mile portion of the existing road. Starting at Summerset Ride Lane, the road will be widened from a two-lane asphalt road to a four-lane concrete boulevard. The final 0.17-mile portion of the road will be shifted 500 feet to the west to align with the new section of Katy-Gaston Road south of FM 1093.
Timeline: July 2016-January 2017 Cost: $1.3 million Funding sources: Fort Bend County