Brinkley Sargent Wiginton Architects, or BSW, presented additional design plans for a proposed new justice center during a Montgomery County commissioners workshop on Nov. 19.
The workshop was scheduled to gather feedback from commissioners on four options for the new facility. According to the presentation, the total project cost is estimated at $496 million.
What happened?
The current projections are for a 481,000-square-foot justice center to meet expected needs in 2050, according to information presented at the meeting. There are currently 17 courtrooms in use with an 18th coming in the future, but 23 are needed now, according to discussion at the meeting.
By 2050, a total of 42 courtrooms and two specialty court spaces will be needed, according to projections. The 40-year-old jail also faces capacity and infrastructure problems as well as inmate transfer delays to the Texas Department of Criminal Justice. The number of annual case filings handled in the county is projected as follows:
2025: 34,948
2050 (projected): 72,133
“Our plan that we are going to be talking about and showing you numbers on [is] assuming that each associate judge has a dedicated courtroom as well as every seated elected judge,” BSW Principal Gina Irwin said.
Also worth noting
Courts account for two-thirds of the space. However, criminal courts alone comprise 30% of that, according to the presentation. The total gross square footage includes:
BSW Vice President Ryan Mclemore provided a site analysis outlining the constraints on the site, noting that the last time they presented information to commissioners, they discussed the possibility of closing down North San Jacinto Street, which would open up valuable real estate to allow the building to grow and be the size the county needs it to be.
“It’s still a great option, but what maybe wasn’t considered was the utilities that happen underneath North San Jacinto. Some of the options that you will see leave those in place, some of those options that you propose suggest relocating,” Mclemore said. “Both options can be done.
It's a budget decision. It's a decision about what's right for the building, what's right for the county.”
Among some of the constraints that need to be addressed for the building are setbacks on Philip Street and on all sides of the building, Mclemore said. Architects are looking at a 20-foot minimum, but it could be upward of 40 feet, he said. Utilities are also a factor in what the cost will be, Mclemore said.
What else?
Commissioners will still need to decide how many floors they’d like the building to have. According to the BSW presentation, there are four draft options to consider for the new justice center:
Option A: 13 floors, 44 courts, 52 secure parking spaces
Option B: 10 floors, 44 courts, 42 secure parking spaces
Option C: 8 floors, 44 courts, 50 secure parking spaces
Option D: 10 floors, 44 courts, 46 secure parking spaces
Stay tuned
After workshop discussion, commissioners and BSW agreed the firm would present additional design and cost information, including new facility options, at the Dec. 17 Commissioners Court.