1. First Street
Construction is nearly complete on the new road along First Street approved by Katy City Council at the start of the year. Poor weather affected construction, but the city anticipates June completion. The two-lane concrete road runs parallel to the railroad track along Hwy. 90 and stretches from Cane Island Parkway to the Houston Lighting & Power Co. railroad crossing to the east.
Timeline: April 8–June Cost: $566,851 Funding Sources: Katy Development Authority (via Metropolitan Transit Authority of Harris County funds)
2. Spring Green Boulevard roundabout at Katy Flewellen Road
Plans are near completion for a roundabout at the intersection of Spring Green Boulevard, Katy Flewellen Road and Cinco Trace Boulevard. The project is expected to open for construction bidding in July. Total construction time is estimated at seven months.
Timeline: July 2015–April 2016 Cost: $2.77 million Funding Sources: Fort Bend County, private developers