1. FM 1488 widening west of Magnolia
Project: Between the Waller County line and FM 1774, FM 1488 is being widened from two to four lanes with a continuous left turn lane.
Update: This project is 98% completed, according to a June 3 media update from the Texas Department of Transportation.
- Timeline: November 2020-third quarter 2025
- Cost: $35.35 million
- Funding source: state funds
Project: The project will build a median from Mostyn Drive to I-45.
Update: The project is 73% complete, as of the most recent update available from TxDOT.
- Timeline: November 2023-second quarter 2026
- Cost: $10.96 million
- Funding sources: state, federal funds
Project: FM 1488 is being widened from two to four lanes with a continuous left turn lane between FM 1774 to west of FM 149.
Update: According to a June 3 media update from TxDOT, this project is 58% complete.
- Timeline: June 2022-third quarter 2027
- Cost: $48.3 million
- Funding source: state funds