FM 1488 widening west of Magnolia
Project: Between the Waller County Line and FM 1774, FM 1488 is being widened from two to four lanes with a continuous left-turn lane.
Update: This project is 91% completed, according to an August media update from the Texas Department of Transportation.
- Timeline: November 2020-fourth quarter 2024
- Cost: $35.35 million
- Funding source: state funds
Project: FM 1488 is being widened from two to four lanes between FM 1774 and west of FM 149.
Update: According to an August media update from TxDOT, this project is 50% completed.
- Timeline: June 2022-first quarter 2025
- Cost: $48.28 million
- Funding source: state funds
Project: Between I-45 and FM 1488, the lanes on Hwy. 242 are being widened using existing right of way, according to prior reporting.
Update: According to an August media update from TxDOT, this project is 31% completed.
- Timeline: October 2023-first quarter 2026
- Cost: $29.1 million
- Funding sources: federal, state funds
Project: FM 1486 is undergoing overlay and base repairs between Hwy. 105 and FM 1774.
Update: This project is 99% completed, according to an August media update from TxDOT.
- Timeline: October 2023-third quarter of 2024
- Cost: $4.57 million
- Funding source: state funds