Ongoing projects
1. FM 1488 west widening
Project: The project will widen FM 1488 on the west side of Magnolia from the Waller County line near Joseph Road to FM 1774.
Update: The project is 74% complete, as of a Jan. 2 update from TxDOT.
- Timeline: November 2020-second quarter 2024
- Cost: $35.3 million
- Funding source: TxDOT
Project: The project will widen FM 1488 from two lanes to four lanes with a continuous left-turn lane between FM 1774 in Magnolia and west of FM 149.
Update: The project is 36% complete, as of a Jan. 2 update from TxDOT.
- Timeline: June 2022-first quarter 2025
- Cost: $48.28 million
- Funding source: TxDOT
Project: This project will add a raised median along FM 1488 east of Magnolia. Crews will construct a raised median along FM 1488 from Mostyn Drive in Magnolia to I-45.
Update: The project is 29% complete, as of a Jan. 2 update from TxDOT.
- Timeline: November 2023-fourth quarter of 2025
- Cost: $10.22 million
- Funding sources: TxDOT, federal