A project to widen FM 1488 is taking shape in Magnolia between FM 1774 and west of FM 149. The project will widen FM 1488 from two lanes to four lanes with a continuous left-turn lane and was 22% complete as of May 4.
Timeline: June 2022-first quarter 2025
Cost: $48.28 million
Funding source: Texas Department of Transportation
FM 1488 at Waller County line
A second project by TxDOT to widen FM 1488 from the Waller County line near Joseph Road to FM 1774 in the city of Magnolia was 64% complete as of a May 4 update from TxDOT, the latest available. The project will widen FM 1488 from two lanes to four lanes with a continuous left-turn lane.
Timeline: November 2020-third quarter 2023
Cost: $30.33 million
Funding source: TxDOT