FM 1488 widening

The Texas Department of Transportation is widening FM 1488 from two to four lanes from the Waller County line to FM 1774 in Magnolia. The project was 33% complete as of TxDOT’s Feb. 7 update.

Cost: $30.24 million

Timeline: Nov. 23, 2020-first quarter 2023

Funding source: TxDOT


FM 2978 widening

The project to widen FM 2978 from FM 1488 south to near Hardin Store Road, was 97% complete as of TxDOT’s Feb. 7 update. The project will widen the stretch of road from two lanes to four. The project had previously been delayed and expected to be completed by the fourth quarter of 2021.

Cost: $22.79 million

Timeline: Sept. 4, 2018-first quarter 2022


Funding sources: state, federal funds