The Texas Department of Transportation is working to reverse the Hwy. 249 northbound entrance and exit ramps between Jones Road and Spring Cypress Road. According to TxDOT Public Information Officer Danny Perez, the project will reverse the existing entrance/exit ramp configuration to an exit/entrance configuration and shift the new exit ramp to the south to eliminate the queue of vehicles that previously formed from the frontage road back to the Hwy. 249 main lanes because of the exit ramp being close to the signalized intersection at Hwy. 249 and Spring Cypress Road. Community Impact Newspaper previously reported the project was set to finish in July, but the completion date has been pushed to September.

Timeline: April 20-early September

Cost: $2.2 million

Funding source: TxDOT