The Texas Department of Transportation's $12.87 million widening of FM 2978 from two to four lanes between Conroe-Hufsmith Road and south of Dry Creek—Segment 1—was 62% complete as of mid-January, according to TxDOT. The widening of FM 2978 continues from south of Dry Creek to FM 1488, which was 38% complete in mid-January.

Timeline: January 2018-third quarter 2020 (Segment 1), September 2018-second quarter 2021 (Segment 2)

Cost: $12.87 million (Segment 1), $21.29 million (Segment 2)

Funding source: TxDOT