1. Texas Department of Transportation crews are replacing the Spring Creek bridge and widening it from two lanes to four lanes. The $7.6 million project was 12 percent complete in mid-February. Estimated timeline: October 2018-third quarter 2020 2. Crews are working on a two-phase project to widen FM 2978 from two lanes to four lanes between FM 1488 and Hufsmith-Conroe Road in the Magnolia area. The $33.8 million project is under construction by TxDOT. Estimated timeline: January 2018-second quarter 2021 3. The $4.7 million widening of Hufsmith-Kohrville Road from two to four lanes between Mahaffey Road and FM 2920 in Tomball was expected to be complete March 1, Harris County Precinct 4 officials said. The project adds a traffic signal at Mahaffey Road. Estimated timeline: January 2018-first quarter 2019