Magnolia City Council received an update on the progress of three wells in the works—No. 7, No. 8 and No. 9—from City Engineer Mike Kurzy at its May 9 meeting.
The gist: Wells No. 7 and 8 are under construction, while a hydrogeological report and design plans are being prepared for Well No. 9, Kurzy said.
- Well No. 7 is anticipated to be completed by the end of the month.
- Well No. 8 is anticipated to be completed in September or October.
- Well No. 9 is anticipated to be completed in late fall 2024.
How we got here: The city of Magnolia is under a temporary development moratorium—originally enacted last December and extended in April—due to not having enough water capacity.