1. Wingstop: 13654 FM 1488, Ste. 300, Magnolia
Type of work: new construction
Timeline: July 1-Oct. 1
Estimated cost: $150,000
2. Jersey Mike's Subs: 25517 N. Grand Parkway W., Tomball
Type of work: renovation/alteration
Timeline: July 26-Sept. 20
Estimated cost: $250,000
3. Chick-fil-A: 6543 FM 1488, Magnolia
Type of work: renovation/alteration
Timeline: Nov. 5-Nov. 15
Estimated cost: $300,000
4.Genesis Clinic: 26940 Kuykendahl Road, Tomball
Type of work: new construction
Timeline: Aug. 1-Oct. 31
Estimated cost: $2.8 million
5. Knotts Tamina: 32122 Tamina Road, Magnolia
Type of work: new construction
Timeline: Aug. 14-Dec. 28
Estimated cost: $462,150