1. Spring Rolling: 13740 Jordan Lewis Way, Ste. 100, Magnolia
Type of work: new construction
Timeline: July 5, 2022-July 5, 2023
Estimated cost: $150,000
Square footage: 2,922
Scope: build-out for restaurant
2. The Toasted Yolk Magnolia: 9533 FM 1488, Ste. 400, Magnolia
Type of work: renovation
Timeline: Sept. 1, 2022-Feb. 1, 2023
Estimated cost: $11.5 million
Square footage: 4,317
Scope: build-out of space for new restaurant
3. Tomball medical office building: 24429 Hwy. 249, Tomball
Type of work: new construction
Timeline: Oct. 1, 2022-Dec. 1, 2023
Estimated cost: $6.5 million
Square footage: 36,500
Scope: new medical office building
4. The Offices on Dowdell: 7630 Dowdell Road, Tomball
Type of work: new construction (three buildings)
Timeline: Oct. 1, 2022-Aug. 31, 2023
Estimated cost: $1.16 million
Square footage: 3,318-3,930
Scope: new general office buildings
5. Master Mini Storage: 14122 Hirschfield Road, Tomball
Type of work: new construction
Timeline: Oct. 1-Dec. 31
Estimated cost: $300,000
Square footage: 11,250
Scope: add two new climate-controlled storage buildings and one non-climate-controlled building
6. Washateria: 10002 FM 2920, Ste. 200, Tomball
Type of work: new construction
Timeline: Nov. 1, 2022-Dec. 1, 2023
Estimated cost: $150,000
Square footage: 2,500
Scope: new Washateria lease space
7. FuelMaxx 87 Convenience Store: 10002 FM 2920, Tomball
Type of work: new construction
Timeline: Nov. 1, 2022-Dec. 1, 2023
Estimated cost: $900,000
Square footage: 5,490
Scope: convenience store building
8. Billiard Factory: 2013 S. Persimmon St., Tomball
Type of work: new construction
Timeline: Nov. 14, 2022-May 22, 2023
Estimated cost: $5.66 million
Square footage: 72,750
Scope: new corporate office/distribution center for the Billiard Factory
9. Della Casa Pasta: 1599 Hicks St., Tomball
Type of work: renovation
Timeline: Sept. 29-Dec. 16
Estimated cost: $150,000
Square footage: 2,300
Scope: renovation of space in strip center
10. Trinity Print Media: 17444 FM 2920, Bldg. 1, Tomball
Type of work: new construction
Timeline: Oct. 3-Nov. 1
Estimated cost: $130,000
Square footage: 6,000
Scope: office build-out in existing building
11. Wendy's: 13660 FM 1488, Magnolia
Type of work: new construction
Timeline: Sept. 12, 2022-Sept. 12, 2023
Estimated cost: $750,000
Square footage: 2,300
Scope: new fast-food restaurant
12. Nails R Us Nail Salon: 3774 Jordan Lewis Way, Magnolia
Type of work: new construction
Timeline: July 25, 2022-March 25, 2023
Estimated cost: $195,000
Square footage: 3,000
Scope: new build-out for nail salon