Curious as to what new businesses and renovations are underway or coming to Tomball and Magnolia? The following projects have been filed in the last month through the Texas Department of Licensing and Regulation. The following information may be subject to change.
1. Montgomery Magnolia Self-Storage: 33319 Beat Branch Lane, Magnolia
Type of work: new construction
Timeline: Sept. 1, 2022-July 31, 2023
Estimated cost: $6 million
2. Christian Brothers Automotive: southeast corner of FM 1488 and Spur 149, Magnolia
Type of work: new construction
Timeline: Jan. 1, 2023-Aug. 4, 2023
Estimated cost: $900,000
3. ClearWater Magnolia Car Wash: 7424 FM 1488, Ste. A, Magnolia
Type of work: new construction
Timeline: Nov. 1, 2022-July 31, 2023
Estimated cost: $1.5 million
4. Tomball 360: 15800 FM 2920, Tomball
Type of work: new construction
Timeline: Sept. 1, 2022-April 1, 2023
Estimated cost: $30.2 million
5. Alamo Title: 9116 N. Grand Parkway W., Ste 800, Tomball
Type of work: new construction
Timeline: July 15-Oct. 15
Estimated cost: $180,000
6. IMS Landscape Services Parking Structure: 18110 Juergen Road, Tomball
Type of work: new construction
Timeline: Aug. 8-Oct. 2
Estimated cost: $102,000
7. Clean Car Wash: intersection of Hwy. 249 and Tomball Parkway, Tomball
Type of work: new construction
Timeline: July, 1, 2022-March 31, 2023
Estimated cost: $2.7 million
8. Kobs Road Business Park Building B: 22502 Kobs Road, Bldg. B, Tomball
Type of work: new construction
Timeline: July 25, 2022-July 25, 2023
Estimated cost: $871,875
9. Magnolia Office Park Building 10: 31332 Nichols Sawmill Road, Magnolia
Type of work: new construction
Timeline: Aug. 1-Nov. 15
Estimated cost: $550,000
10. Vivint: 5417 FM 1488, Ste. D, Magnolia
Type of work: renovation/alteration
Timeline: July 25-Sept. 30
Estimated cost: $90,000