Curious as to what new businesses and renovations are underway or coming to the Tomball and Magnolia area? The following projects have been filed in the last month through the Texas Department of Licensing and Regulation. The following information may be subject to change.

1. Taco Bell: 32011 Decker Prairie Road, Pinehurst

Type of work: new construction

Timeline: July 1-Nov. 15


Estimated cost: $375,000

2. Alamo Title: 9116 N. Grand Parkway W., Ste. 800, Tomball

Type of work: new construction

Timeline: July 15-Oct. 15


Estimated cost: $180,000

3. Clean Car Wash: Hwy. 249 & Tomball Pkwy., Tomball

Type of work: new construction

Timeline: July 1, 2022-March 31, 2023


Estimated cost: $2.7 million

4. Kobs Road Business Park: 22502 A Kobs Road, Tomball

Type of work: new construction

Timeline: July 25, 2022-July 25, 2023


Estimated cost: $871,875

5. Sitework: 1623 S. Cherry St., Tomball

Type of work: new construction

Timeline: Sept. 1, 2022-June. 1, 2023


Estimated cost: $1.6 million

6. ADV Integrity: 4027 Pinehurst Meadow, Magnolia

Type of work: new construction

Timeline: May 30-Oct. 17

Estimated cost: $1.2 million

7. Myrtle Gardens: Myrtle Gardens Blvd., Magnolia

Type of work: new construction

Timeline: Aug. 1-Nov. 1

Estimated cost: $385,450

8. First Community Credit Union: 32803 FM 2978, Magnolia

Type of work: new construction

Timeline: Aug. 1, 2022-March 1, 2023

Estimated cost: $3.2 million

9. Magnolia Village Retail Center: 13370 FM 1488, Magnolia

Type of work: new construction

Timeline: June 1-Dec. 1

Estimated cost: $1.6 million

10. Jiffy Lube: 218 Smith Road, Magnolia

Type of work: new construction

Timeline: June 30-Oct. 31

Estimated cost: $900,000