Curious as to what new businesses and renovations are underway or coming to the Tomball and Magnolia area? The following projects have been filed in the last month through the Texas Department of Licensing and Regulation. The following information may be subject to change.
1. Taco Bell: 32011 Decker Prairie Road, Pinehurst
Type of work: new construction
Timeline: July 1-Nov. 15
Estimated cost: $375,000
2. Alamo Title: 9116 N. Grand Parkway W., Ste. 800, Tomball
Type of work: new construction
Timeline: July 15-Oct. 15
Estimated cost: $180,000
3. Clean Car Wash: Hwy. 249 & Tomball Pkwy., Tomball
Type of work: new construction
Timeline: July 1, 2022-March 31, 2023
Estimated cost: $2.7 million
4. Kobs Road Business Park: 22502 A Kobs Road, Tomball
Type of work: new construction
Timeline: July 25, 2022-July 25, 2023
Estimated cost: $871,875
5. Sitework: 1623 S. Cherry St., Tomball
Type of work: new construction
Timeline: Sept. 1, 2022-June. 1, 2023
Estimated cost: $1.6 million
6. ADV Integrity: 4027 Pinehurst Meadow, Magnolia
Type of work: new construction
Timeline: May 30-Oct. 17
Estimated cost: $1.2 million
7. Myrtle Gardens: Myrtle Gardens Blvd., Magnolia
Type of work: new construction
Timeline: Aug. 1-Nov. 1
Estimated cost: $385,450
8. First Community Credit Union: 32803 FM 2978, Magnolia
Type of work: new construction
Timeline: Aug. 1, 2022-March 1, 2023
Estimated cost: $3.2 million
9. Magnolia Village Retail Center: 13370 FM 1488, Magnolia
Type of work: new construction
Timeline: June 1-Dec. 1
Estimated cost: $1.6 million
10. Jiffy Lube: 218 Smith Road, Magnolia
Type of work: new construction
Timeline: June 30-Oct. 31
Estimated cost: $900,000